Excelsior Mining Impresses Markets By Receiving APP Permit For Gunnison: Permitting Of First Greenfield Copper ISR Project Within Reach Now

Johnson Camp Mine

After having received the Aquifer Protection Permit (APP) draft by the Arizona Department of Environmental Quality (ADEQ) for the Gunnison Copper project on  June 14, which had to undergo a public comment period of a month and final decision making after this, Excelsior Mining (MIN.TO, US ticker EXMGF) finally received the APP on September 5, which is one of the two biggest possible catalysts for this copper developer, and very good news. The other catalyst in this regard will be the granting of the Underground Injection Control (UIC) permit, which is issued by the Environmental Protection Agency (EPA). There has always been a significant amount of doubt if Gunnison could be permitted, as it would be the first greenfield copper ISR project in the USA to do so, and Arizona doesn't have a reputation of going easy on permitting anyway.

In comparison, the nearby Florence project of Taseko (former Curis) received just temporary operating permits in December 2016 for their test facility, whereas Gunnison is in the process of receiving operating permits for the entire project, of which the granted APP is the first of the two major permits needed. Notwithstanding this, Excelsior management always has been very confident on the entire permitting process, probably strengthened in their belief by the impressive skills and experience of VP Sustainability Rebecca Sawyer, who has been leading the process from the beginning, and apparently rightly so.  

Although the share price has been going up steadily the last year, building one of the best charts in the industry, it is not really clear to me what part of this has been caused by investors anticipating the grant of permits:

Share price Excelsior Mining (MIN.TO); 1 year period

As you probably know, copper prices have been going up in that period as well, based on growing demand, a lower dollar, strikes, power outages and lower grade, and roughly seem to follow the same pattern as the Excelsior chart:

This could indicate a lot more re-rating potential, as it looks to me if the entire chance on permitting success hasn't been priced in yet. As I will show in a bit, the NPV value of Gunnison at current copper prices is still much higher than the current market cap, which will no longer make much sense as soon as the project would be fully permitted.

Let's discuss the APP permit first here, to get things clear. The news release shows that it isn't the definitive permit yet:

"The ADEQ has issued Excelsior a Grant Letter, which remains appealable under specific circumstances for 30 days. After the close of the appeal period, the APP will be fully executed and the permit will then be active."

My first question to management was what they were anticipating with this appeal period for potential risks. Their answer was pretty straightforward, there could be appeals although they don't expect any, but in any case they expect a 100% chance on receiving the APP before the end of this year. Such an appeal would most likely take a month. On my follow up question why they are so convinced again, the answer was equally straightforward: they firmly believe there is nothing substantive contained within the 5 comments that were received. To me this looks if the APP is already very close to the finish line, and for about 95% a done deal, which is very important for the company.

The federal UIC permit is expected by management to follow the same trajectory, and Excelsior anticipates the draft permit to be received in September, with the permit to be issued two months later in November. I am convinced that negotiations on any financing package will significantly pick up speed when both APP and UIC permits are arranged. Initial capex is very low at $47M as ramping up is staged, so I don't expect any problem with arranging packages here, and any equity part, if necessary at all, will hardly cause any dilution at current or higher share prices. And even if financiers decide to start out at a much larger capacity to profit from high copper prices, and would need a much bigger equity component, adding let's say 30-40M shares to the current 183M F/D figure is still very modest anyway.

Let's see what happens in a quick sensitivity analysis on Gunnison, when using the current 183M F/D shares without any dilution, and for example a 210M F/D share count, assuming in both cases a fully financed and constructed project, ready for commencing commercial production. In that case I estimate the market cap to be equal to full post-tax NPV7.5 (although I have to add that I don't consider Arizona a risky jurisdiction when operating, and a 5 or 6% discount could be warranted as well although opinions differ on this subject). In the following table MM means million, F/D fully diluted shares and PPS price per share:

At a current share price of C$1.32 and a current copper price of $3.14/lb Cu, it will be clear why there is still so much upside for Excelsior, and why it most likely will be significantly re-rated between receiving permits and production. Just a fully permitted project at FS-stage, which is also very profitable and has a low capex, could rate anywhere between 30-50% of NPV, so I expect Excelsior to trade at least around C$2.00 when both permits are granted. I don't expect any issues with arranging financing or with construction, as the company has powerful backing by Greenstone who is a controlling shareholder at 50.4%, and wants to see this going into production as soon as possible. The future is looking bright for this developer, which has probably the most profitable copper project on the planet.       

I hope you will find this article interesting and useful, and will have further interest in my upcoming articles on mining. To never miss a thing, please subscribe to my free newsletter, and follow me on Seekingalpha.com, in order to get an email notice of my new articles soon after they are published.

Disclaimer:

The author is not a registered investment advisor, and currently has a long position in this stock. Excelsior Mining is a sponsoring company. All facts are to be checked by the reader. For more information go to http://www.excelsiormining.com/ and read the company’s profile and official documents on www.sedar.com, also for important risk disclosures. This article is provided for information purposes only, and is not intended to be investment advice of any kind, and all readers are encouraged to do their own due diligence, and talk to their own licensed investment advisors prior to making any investment decisions.

 

 

This newsletter/article is not meant to be investment advice, as Criticalinvestor.eu (from now on website, newsletter, and all persons or organisations directly related to it, for example but not limited to: owner, editor, the Seekingalpha author The Critical Investor, publisher, host company, employees, associates, sponsoring companies)  is no registered investment advisor. Therefore it is not intended to meet your specific individual investment needs and it is not tailored to your personal financial situation. This newsletter/article reflects the personal and therefore subjective views and opinions of Criticalinvestor.eu and nothing else. The information herein may not be complete, up to date or correct. This newsletter/article is provided in good faith but without any legal responsibility or obligation to provide future updates.

Through use of this website and its newsletter viewing or using you agree to hold Criticalinvestor.eu harmless and to completely release them from any and all liability due to any and all loss (monetary or otherwise), damage (monetary or otherwise), or injury (monetary or otherwise) that you may incur.

You understand that Criticalinvestor.eu could be an investor and/or active trader, meaning that Criticalinvestor.eu could buy and sell certain securities at all times, more specific any or all of the stocks mentioned in own newsletters/articles and other own content like the Watchlist, Leveraged List, etc.

No part of this newsletter/article may be reproduced, copied, emailed, faxed, or distributed (in any form) without the express written permission of Criticalinvestor.eu. Everything contained herein is subject to international copyright protection. The full disclaimer can be found here.